11. Flexible Hose Installation
Apply thread sealant onto the threads of the spray shank.
Connect the flexible hose from the transfer valve onto the spray
shank.
Connect the flexible hoses from the end body outlets to the
supply tee inlets.
Thread a flexible hose onto the supply tee outlet.
Slide the gasket onto the transfer valve/vacuum breaker shank.
Connect the flexible hose from the supply tee inlet onto the
transfer valve/vacuum breaker shank.
Spray Head
Assembly
Shank
Apply Thread
Sealant.
Plastic
Flexible
Hose
Transfer Valve/
Vacuum Breaker
End Body
Valve
Gasket
Supply Tee